Skip directly to content

UPM modular pipe bridge

During the year 2015 UPM executed an expansion investment project where the plant capacity was increased by a third up till 700 000 tons.


Fabrication of the bridge sections and installation of pipes, insulation and cable trays were completed in the workshop. Bridge sections was lifted directly from the transportation carriage. Only the bridge section pipe joints were welded and insulated in site conditions. Installation at the site was done in only three weeks.