Northvolt

Northvolt
During the years 2020 and 2021 Fineweld had a turn key delivery of a cathode material plant to Northvolt in Skellefteå Sweden.

Project was executed in alliance with ABB and Sweco. Sweco took care of engineering and ABB delivered plant electrification, instrumentation and automation. All mechanical plant construction was carried out by Fineweld.

Fineweld delivery consisted of ca 60 km piping and 2800 tons of steel structures. Main part of plant auxiliary equipment was purchased by Fineweld. Fineweld took care of complete installation of Main and auxiliary equipment.

Share with your network